Product Team Update October 5, 2018

 
product.jpg
 

THIS WEEK'S UPDATE

  • Finalize SmartSheet project plan for full facility build out

  • Wash and centrifuge solids for enzymatic hydrolysis trials at INRS

  • Finalize plans for moving to Grimsby

  • Review/finalize contract for 20HL brewhouse

  • Finalize NSERC Engagement Grant

  • Set up a call with Evhert and science team to determine their capabilities for design/modeling the hemp treatment plant.

LOOKING FORWARD

  • Enzymatic hydrolysis assessment 1 of 4

  • Continue developing lab detail drawings

  • Attend Pack-Expo in Chicago to source packaging equipment suppliers.

  • Continue preparing Hunter Road for occupancy

THINGS WE NEED HELP WITH

  • We are still looking for financing for the brewery equipment