Product Team Update August 17, 2018

 
product.jpg
 

THIS WEEK'S UPDATE

  • Engaged KSH to assist in the design and construction of the Grimsby location.
  • Engaged Krones and DME to develop proposals for the brewhouse.
  • Interviewed a potential employee for lead extraction role

LOOKING FORWARD

  • Finalize the laboratory equipment list and provide spec sheets to KHS. This will allow them to develop a draft layout for review with the team.
  • Further discussions with DME and Krones on the brewhouse requirements. Source 1 – 2 more bidders for the brewhouse.
  • Have a discussion with David Hyde on the security requirements for the Grimsby location.
  • Update the Kanban board and start the layout out the project Gantt charts in Smartsheet.
  • Work with the marketing team to develop the packaging requirements.

THINGS WE NEED HELP WITH

  • We would like to develop a list of quality subtrades to submit proposals to:
    • Mechanical
    • Electrical
    • HVAC
    • General construction, etc.